उत्तर प्रदेश सरकार  |  Government of Uttar Pradesh

Solar Rooftop Plant (Off-Grid) Govt/Semi Govt Buildings

Off-grid solar power plants are installed by UPNEDA based on the proposals and funds made available by various state departments. An Off-grid solar power plant consists of a battery backup for approximately 4-6 hours, which is useful for those government buildings where reliable grid electricity is not available.

The following rates have been discovered by UPNEDA through tender, which are valid till February/March 2026:

Sr.No. Plant Capacity (kW) Discovered Price incl. GST (ALMM listed DCR) (Rs./kW) Discovered Price incl. GST (ALMM listed Non-DCR) (Rs./kW)
1 1 kW to 10 kW 106000 97000
2 11 kW to 50 kW 99000 92000
3 51 kW to 75 kW 97000 90000

In the financial year 2024-25, the progress details of the total installation of solar off-grid plants are as follows, which include the works carried out against the funds received from the concerned departments like Health for CHCs/ PHCs and Ayushman Arogya Mandir sites under the National Health Mission, MLA/ MP fund, etc

Sr.No. Source of Fund Total Ordered Plants Capacity (kW) Work Completed Work in Progress
1 Various Departments 581 2126 359 222
Last Updated on Page :